Examples For Auto-Scheduling

Below are just a few examples of how to use the Auto-Schedule and Dependency features to automatically schedule your activities on the calendar. We recommend only assigning one dependency to an Activity. See Related Articles below for more help with Dependencies.


Example 1: Fabrication automatically scheduled based on Template date

Fabrication Dependency

Once the Template date is entered, the Fabrication date is automatically populated.

Auto Schedule Example

Example 2: Fabrication automatically scheduled based on Install date.

install date dependency

Once the Install date is entered, the Fabrication date is automatically populated.

Job Activities